国产亚洲精品女人久久久久久,中文字幕综合97,久久久久久久丫久久久极品,欧美日韩国产成人自拍

phone/wechat/what's app: +86-18653810085

Email: hongyuanmakela@163.com

Taian Hongyuan Geosynthetics Co., Ltd.
Tel:18653810085

Technical Services Current Position:Home > Technical Services

Precautions for GCL construction

Release time:2020-4-7    This article is read :5674 Times

GCL construction

Precautions for GCL construction

1. The site should be kept relatively dry during construction, and the base surface can be wet, but there should be no water accumulation.

2. The laying, connection and interface of the GCL should meet the design requirements and construction specifications, and be firm and stable, without hollowing, damage, slippage, warping, wrinkling and other phenomena.

3. If the impermeable blanket is damaged during the laying process, a pair of GCLs larger than the damaged surface by 30cm ~ 50cm must be cut and covered, and the surrounding area should be coated with bentonite waterproof slurry. 4. After the GCL is laid and inspected, the construction of backfill shall be carried out simultaneously to avoid trample and damage.

5. The GCLs should be stacked in the designated place on the site, and be cushioned to maintain a certain distance from the ground, and covered with plastic film to avoid rainwater immersion, sunlight and moisture.

6. If it rains during the construction process, it should be covered immediately with plastic film materials or rain shielding materials to avoid rainwater soaking and washing the waterproof layer and affecting the construction quality. When the rain is large and the bentonite swells by more than 300%, it should be laid again.

7. The equipment or truck cannot be placed directly on the GCL, and the cover must be set to work.

8. When laying, it is strictly forbidden to put an open flame or cigarette butt on any side of the GCL, and it is strictly forbidden for construction personnel to wear spike shoes.

9. During the construction, if the construction party encounters unclear drawings or the construction site does not conform to the design of the drawings, it should be notified to the designer in time and properly resolved through consultation.

10. For other unfinished matters, the national and local acceptance standards and operating specifications shall be followed during construction.

Precautions for GCL construction
Previous:Comparative analysis of several geotextile materialsnext:Construction notes of GCL

Contact Us:

WeChat public account

Taian Hongyuan Geosynthetics Co., Ltd.

Phone / Wechat / What's app:+86-18653810085

Telephone / Fax: + 86-538-6598877

Email:  hongyuanmakela@163.com

Website: tehfbbd.cn

Address: Jinghua Industrial Zone, NO. 88 Leigushi Street, Taishan Industrial Park, Taian City, Shandong Province, China

Copyright? Taian Hongyuan Geosynthetics Co., Ltd.            Lugong Network Security No. 37090202000491            Lu ICP No. 16042524-1           公示信息

高级搜索91在线观看| 国产原创Av无码| 《国产欧美日韩中文久久》| 国产偷人视频| 调教视频一区二区| 天天舔天天吃天天射| 有码韩国一区二区三区| a√久在线观看| 天天在线日韩AV中文字幕一区| 九九性高潮免费| 欧美精品成人a v| 日本色视| 亚洲妓女色情网| 加勒比三区人妻| 91欧美高清无码| 久久高潮大片| 日B免费免费观看视频| 亚洲精品一二三四区| 强开小嫩苞一区二区三区免费| 天天干天天爱天天爽天天干很| 偷拍Av第一区| 超碰po| 大香蕉性感国产| 精品国产一区2区三区| 色综合国产一区二区| 免费麻豆美女黄色| 好吊妞视频免费| seAV一区二区| 二区三区免费不卡视频| 日本久久午夜精品| 日本中文三级电影| 日韩精品9区| 欧美极品黄片| 肏屄狠狠肏| 欧洲成人无码在线| aaa久久久国产| 日本久久久久久久久久日本| 暖暖视频一区二区| 久久久少妇骚逼久久久久久久久| 一级伦理网站| 婷婷激情五月天欧美视频|